How long does a building permit take in Florida?

Florida law sets deadlines for local governments to approve or deny building permits: 30 business days for most homes and residential trade permits. What the statute says, what counts as a complete application, and what happens when a city misses the deadline.

In Florida, a local government generally has 30 business days to approve, approve with conditions, or deny a complete building permit application for a single-family home or a residential roofing, mechanical, electrical or plumbing permit on a building under 7,500 square feet. That deadline comes from state law, section 553.792 of the Florida Statutes. Many simple permits, such as a like-for-like A/C change-out, are issued much faster, often the same day or within a few days, depending on the city or county.

This guide explains the statutory timeframes, what starts the clock, and what happens if a building department misses a deadline. It is general information based on the 2025 statute text, not legal advice. Local procedures vary, and the building department that will issue your permit is the authority for your project.

The statutory deadlines

Section 553.792(1)(a) sets the maximum time a local government has after it receives a complete and sufficient application, when the applicant uses the local government's own plans reviewer:

Type of application Deadline
Residential units, including single-family homes, and accessory structures, alarm, electrical, irrigation, landscaping, mechanical, plumbing or roofing permits, for buildings under 7,500 sq ft 30 business days
The same permit types for buildings of 7,500 sq ft or more 60 business days
Signs, and nonresidential buildings under 25,000 sq ft 60 business days
Multifamily buildings up to 50 units; site-plan approvals and subdivision plats without a public hearing; lot grading and site alteration 60 business days
A site-specific permit issued under a master building permit 12 business days

A local ordinance can set shorter timeframes, and many building departments issue routine permits well inside these limits.

What starts the clock

The deadline runs from receipt of a complete and sufficient application, so completeness matters:

  • Completeness check: 5 business days. The local government must tell you in writing, within 5 business days of receiving the application, if information is missing. If it does not, the application is deemed complete and accepted.
  • Deficiencies. If the reviewer finds problems, it sends written notice of the deficiencies. You then have 10 business days to submit revisions, or the application can be denied.
  • Review of revisions: 10 business days. The local government then has 10 business days to approve or deny the revised application.

In practice, the biggest delays come from incomplete applications and rounds of revisions, not from the first review.

What happens if a city misses the deadline

Under section 553.792(1)(e), if a local government misses a deadline, it must reduce the permit fee by 10 percent for each business day it is late, unless the applicant agreed in writing to a reasonable extension, the delay was caused by the applicant, or the delay was caused by force majeure or other extraordinary circumstances. If it misses the 10-day deadline to review revisions, the fee reduction is 20 percent per business day.

An applicant may waive the timeframes in writing, but the statute says a local government cannot require a waiver as a condition of accepting or reviewing an application. Some cities, such as Miami and Orlando, publish their own guidance on how they apply these rules.

Typical timelines by job

These are general patterns, not guarantees; every building department publishes its own current review times.

  • A/C change-outs, water heaters, many electrical and plumbing jobs: often issued over the counter or online within days, since they need little or no plan review.
  • Re-roofs: usually quick for a straightforward replacement, but Florida requires specific product approvals and, in high-velocity hurricane zones such as Miami-Dade and Broward, stricter documentation.
  • Pools, screen enclosures, fences and decks: need plan review; weeks rather than days is common, and pool barrier details are a frequent reason for revisions. See Florida pool barrier requirements.
  • New single-family homes: full plan review, usually the longest; the 30-business-day limit applies to homes under 7,500 sq ft once the application is complete.

Florida also allows owners and contractors to use a licensed private provider for plan review and inspections under section 553.791, which can shorten timelines; ask your building department how it handles private provider submittals.

What the permit data shows

Permits are issued every working day across Florida. In the markets we track, the last 30 days saw:

Market Residential permits, last 30 days Roofing Pool & spa New homes
Miami-Dade County, FL 3,770 806 342 158
Miami, FL 782 176 59 29
Orlando, FL 2,487 314 108 42
Hillsborough County, FL 671 n/a 136 264
Port St. Lucie, FL 1,736 224 78 332

Data through Nov 18, 2026. Hillsborough County's feed excludes stand-alone roofing permits. For details by market, see our reports on Miami-Dade pools, Orlando roofing and pools, Tampa-area pools and Port St. Lucie.

What this means for contractors

The issue date is the moment a homeowner's project becomes real. For the contractor who pulled the permit, it is the start of work; for everyone else, it is the best time to reach the household before related decisions are made: pool service before the pool is finished, a fence before the barrier is chosen, gutters before the roofer leaves.

Permitnote reads Florida permit feeds every morning and mails your postcard to each matching household the week its permit is issued, from $149 a month plus $1.19 per card, printing and postage included. Check your area with the free permits near me lookup, or preview a card in the postcard designer.

FAQ

How long does it take to get a roofing permit in Florida?

State law gives a local government up to 30 business days after a complete application for a residential roofing permit on a building under 7,500 sq ft. Many departments issue simple re-roof permits much faster; check your city or county's current review times.

What if my Florida building permit is taking too long?

Ask the building department whether your application was deemed complete and whether any deficiency notice was sent. If the statutory deadline passed without a written extension, section 553.792 requires a fee reduction. For anything beyond that, talk to your contractor or an attorney.

Do these deadlines apply to every Florida city and county?

Section 553.792 applies to local governments statewide, but a local ordinance can set shorter deadlines, and some situations (applicant-caused delays, agreed extensions, extraordinary circumstances) are excepted. Your building department can tell you how it applies the rules.